A Burlington kitchen renovation budget with Gracia usually falls between $40,000 and $140,000+ before HST. Where your kitchen lands in that range depends on five things more than on its size: whether the layout changes, whether a wall comes out, how the range hood vents, whether the electrical service can carry new appliances, and which cabinets and counters you pick. Older homes in Aldershot and Roseland often start higher because of what's behind the walls. Newer homes in Alton and Millcroft usually start lower.
- Our published kitchen range is $40,000 to $140,000+ before HST, plus 13% HST.
- Older homes in Aldershot and Roseland often need wiring, panel or venting work before a cabinet goes in.
- Taking out a load-bearing wall adds engineering, a beam, a City permit and time.
- Cabinetry is usually the biggest single line. Box material, door finish and cabinet height are the main levers.
- Lock in the layout and appliances before you price anything else. Most budget creep starts with late changes.
Our kitchen price range, and what sits at each end
We publish one range for kitchens: $40,000 to $140,000+ before HST. That covers design, demolition, trades, cabinetry, counters, finishes and permits where they're needed. HST of 13% goes on top. When you compare quotes, check what each one actually includes. Many quotes leave out permits, design, electrical upgrades or a contingency.
Prices are still creeping up, just more slowly than a few years ago. In the second quarter of 2026, Statistics Canada's Residential Renovation Price Index showed renovation prices up 2.3% year over year across 15 markets, and up 1.0% in Toronto. You can see the project-level data in Statistics Canada's renovation price table.
| Scope | What it usually includes | Where it tends to land in our range |
|---|---|---|
| Same layout, full replacement | New cabinets, counters, backsplash, lighting, flooring. Plumbing and appliances stay where they are. | Lower end |
| Layout adjusted | Sink or range moves, island added, new circuits, new hood duct run | Middle |
| Open concept | Wall removed with a beam, layout redone, flooring tied into nearby rooms | Upper middle to upper end |
| Full custom | Custom millwork to the ceiling, panelled appliances, stone slabs, electrical service upgrade | Upper end and beyond |
For neighbourhood-level detail, our Burlington kitchen renovation cost guide goes deeper than this post.
How the age of your Burlington house sets the starting point
Two kitchens of the same size can start in very different places. A 1960s or 1970s side-split in Aldershot or Roseland and a 2000s two-storey in Alton or Millcroft show us very different things once the drywall comes off.
| What we check | 1960s–1970s homes (Aldershot, Roseland) | Newer builds (Alton, Millcroft) |
|---|---|---|
| Walls | Closed kitchens. The wall to the dining room is often load-bearing. | Usually already open, so less structural work |
| Wiring | May have aluminum branch wiring, few kitchen circuits, sometimes a 100-amp panel | Copper wiring and a 200-amp panel are common |
| Venting | Short or undersized hood ducts, sometimes none at all | Ducted hoods, but often small ducts sized for builder-grade hoods |
| Floors and ceilings | Out-of-level floors, plaster or older drywall, layers of old flooring | Flatter, but bulkheads and ducts get in the way of tall cabinets |
| Typical surprise | Old plumbing in the walls, patched framing | Builder shortcuts, like a duct crushed in a bulkhead |
Wiring is the big one in older homes. Many Burlington houses from that era have aluminum branch wiring. When we open the walls in a house like that, we price the kitchen circuits new in copper and tell you what we saw in the rest of the house. Then you can decide on the rest with real information, not guesses.
Layout changes and walls
Moving plumbing
Keeping the sink where it is saves money. Moving it a metre along the same wall usually isn't a big deal. Moving it to an island means a new drain and vent run through the floor. If the basement below is finished, that also means opening and repairing the basement ceiling. Island sinks need a venting method the inspector will accept, so we settle that at design, not on install day.
Removing a wall
Opening the kitchen to the dining or family room is the most common request we get in older Burlington homes. If the wall carries load, the job needs an engineer's beam design, a building permit, temporary shoring, the beam (LVL or steel), new posts down to proper bearing, then drywall, flooring and ceiling patching on both sides. The beam is often not the expensive part. The finishing around it is.
Permits take time too. The City of Burlington says that once you submit a complete application, plan review happens within 10 business days. After that, it either issues the permit or sends a list of items to fix. We start drawings while you're still choosing finishes, so the permit is in hand before demolition.
Ventilation: the hood is easy, the duct is the work
You can pick a hood out of a catalogue. Getting the air outside is where the money goes. What decides it:
- Range on an exterior wall: a short, straight run out the back. This is the cheapest option.
- Range on an island or interior wall: the duct goes through ceiling joists or a bulkhead. In bungalows we can sometimes go up through the attic, which needs insulated duct and a proper roof cap.
- Joists running the wrong way: you can't cut through them freely, so the duct may need a bulkhead or a longer route.
- Bigger hoods: high-capacity hoods need a larger duct. For those, we have the HVAC side checked for make-up air before ordering, especially in tight newer homes.
We don't recommend recirculating hoods over gas ranges. They catch grease but don't remove moisture or combustion by-products. If the budget is tight, we'd rather spend on a properly ducted mid-range hood than on a showpiece hood with a poor duct run.
Electrical service and circuits
Modern kitchens draw far more power than the ones they replace. An induction range, wall ovens, a microwave drawer, the dishwasher, the fridge, under-cabinet lighting, pot lights and island outlets each need circuits. In a 1970s house we often find the panel is full, or the service is too small for an induction range plus a future EV charger or heat pump.
Three things decide the electrical budget:
- Panel space. If there's room for new breakers, it's simple. If not, you need a sub-panel or a new panel.
- Service size. Going up in amperage involves the local utility and adds lead time. ESA warns homeowners about anyone who says you don't need to involve your local electric utility to change a panel or upgrade service.
- What's in the walls. Aluminum or ungrounded circuits feeding the kitchen get replaced, not extended.
In Ontario, a building permit doesn't cover electrical work. ESA says the electrical work needs its own permit, separate from your general building permit, and only Licensed Electrical Contractors can legally be hired to do it. Once the installation passes, ESA issues a Certificate of Acceptance. We include that permit in our pricing so it doesn't show up later as an extra.
Cabinetry: usually the biggest line
In most of our kitchens, cabinetry is the largest single cost. What moves the price:
- Box material. Plywood costs more than melamine and holds screws better around sinks and dishwashers. Our breakdown of plywood vs melamine cabinet boxes explains where each one makes sense.
- Door finish. Thermofoil and melamine slab doors sit at the lower end. Painted shaker and acrylic are in the middle. Rift-cut white oak and walnut veneer are at the top.
- Height. Cabinets to an 8-foot ceiling with crown moulding cost less than stacked uppers to a 9-foot ceiling. In Alton and Millcroft homes with 9-foot main floors, that choice shows up quickly on the quote.
- Interior hardware. Drawer bases instead of door bases, pull-out pantries, corner units and built-in organizers add up fast.
- Panelled appliances. Integrated fridge and dishwasher panels look clean, but they add cabinet work and usually require specific appliance models.
If your room has awkward walls, low windows or a bulkhead you can't move, custom kitchen cabinets built to fit often cost less overall than forcing in stock sizes and filling the gaps with filler strips and panels.
Countertops and backsplash
Surface area drives the counter price, but so do details people don't think about:
- Material: quartz is the common middle ground. Porcelain slabs and natural stone like quartzite cost more and take more careful fabrication.
- Seams: a long island that won't fit on one slab means a seam or a second slab.
- Edges and thickness: mitred edges and waterfall ends add fabrication time.
- Cutouts: undermount sinks, cooktops and pop-up outlets each add a charge.
- Full-height backsplash: running the counter material up the wall uses more slab and takes more cutting than tile.
We'd rather put money into a good slab on the island, where everyone sees it, and use a simple, durable tile on the walls than spread a premium material thinly over everything.
Where projects go wrong: what we see on site
These are the patterns we run into most in Burlington kitchens:
- Appliances chosen after the cabinets are ordered. A 36-inch range in a 30-inch opening, or a "counter-depth" fridge that turns out to be standard depth, means remaking cabinets. Pick appliances first and give us the spec sheets.
- Floors not levelled. Floors in older Aldershot and Roseland homes often slope toward the middle of the house. If cabinets go on an unlevelled floor, the counters, dishwasher and toe kicks never sit right. We level first.
- Flooring stopped at the cabinets. If you might change the layout someday, run the new floor under the island too. Patching flooring later costs more and is hard to match.
- Undersized hood ducts kept to save money. A new hood on an old 4-inch duct is loud and doesn't pull well. Replace the duct while the ceiling is open.
- No contingency. In a 1960s or 1970s house, we'd hold 10% to 15% of the budget for whatever turns up in the walls. In a newer home, less is usually fine.
- Bulkheads ignored at design. In newer homes, bulkheads often hide ducts. We confirm what's inside before designing tall cabinets around them.
What we'd do: settle the layout and appliances first, confirm the structure and electrical service second, then choose cabinets and counters to fit the budget that's left. Working in that order keeps most kitchens on budget.
Setting a realistic number for your kitchen
- Decide whether the layout stays or changes. This is the biggest single budget decision.
- Find out if any wall you want gone is load-bearing.
- Check your panel: amperage, free spaces, and whether the house has aluminum wiring.
- Choose appliances, including the hood, and where the duct will run.
- Choose a cabinet tier and counter material that fit what's left.
- Add HST and a contingency that suits the age of your house.
For a first number on your own kitchen, start with the cost estimator on our kitchen renovations page. Then read about our kitchen renovations in Burlington, which covers local permits, house types and the work we do near you.